Justin Hernandez Posted August 6, 2015 Report Share Posted August 6, 2015 Scope of work, change rotted down pipe wire was exposed, install low voltage bonding bridge, install water ground with bonding jumper for previous water softener. Dig a huge 4 foot deep hole which is not easy here in Florida. New number 6 ground wire, replace second ground rod which was rotted out but looks like someone cheated and just used a small piece code is two 8 foot ground rods spaced at 6 feet apart. Pull permits and call in for inspections there is 3 inspections needed for this little job. Quote Link to comment Share on other sites More sharing options...